Date: 06/12/08 20:24
BNSF Seattle, WA construction update
Author: markgillings

There have been big changes north of Lander Street. The yard trackage has been removed to make room for the new ladder.

1) The rest of the Lander Main has been built and the connection made behind me. At left, panels to be removed are still being cut. The Lander Main will be come alive June 16 with speed increases the 17th. South of Royal Brougham, passenger will be 50 MPH with freight at 35(?).

2) The last turnout that remained of the hand-thrown Lander Crossovers is about to be hauled away. At right is one of the Main 1 turnouts that will be reused.

3) Just two minutes later, the 8th Spring Creek Mine to Robert's Bank coal train runs through.








Date: 06/12/08 20:25
Re: BNSF Seattle, WA construction update
Author: markgillings

4) Looking north, it can be seen how the Lander Main follows the new curve and how the 2nd Avenue Yard and old mainlines will be accessed.

5) A little closer. The dwarf signal on the left will govern southward movement into Lander Street from the yard and the right signal will do the same from the Lander Main.

6) Then today, the rest of the dirt was cleared out and a couple more turnout panels were placed. Next week, we can start hooking it all up.








Date: 06/12/08 20:42
Re: BNSF Seattle, WA construction update
Author: RAS

Looking good, Mark! It's cool to see this new trackage in service.

-Rick

Rick Selby
Redmond, WA
Pacific Northwest RPM



Date: 06/12/08 22:18
Re: BNSF Seattle, WA construction update
Author: SPGP9

Thanks, Mark. These are scenes I don't often get to see. Not familiar with a lot of what you guys do so it is nice to view it up close.



Date: 06/13/08 00:21
Re: BNSF Seattle, WA construction update
Author: esorbo

Very interesting! And you're explanations are quite informative. Thank you for sharing!



Date: 06/13/08 13:08
Re: BNSF Seattle, WA construction update
Author: TopcoatSmith

All that loader work looks kinda fun (as long as the groundlings stay outta the way).


TCS - as always, like the excellent reporting and pics



Date: 06/13/08 14:47
Re: BNSF Seattle, WA construction update
Author: ProAmtrak

50 for passenger and 35 for freight, sounds like a Cajon Pass type scenario to me!



Date: 06/14/08 09:39
Re: BNSF Seattle, WA construction update
Author: CyberFoamer

Mark,
What is the benefit the of new mainline route south of King Street? Fewer crossings?

Casey



Date: 06/14/08 15:15
Re: BNSF Seattle, WA construction update
Author: bnsftrucker

CyberFoamer Wrote:
-------------------------------------------------------
> Mark,
> What is the benefit the of new mainline route
> south of King Street? Fewer crossings?
>
> Casey


One of the benefits is the new tracks runs around the coach yard and king station as it used to run between the coach yard and king st station.
The new route allows Amtrak and Sounder to do their switching, washing, and it allows Amtrak to go down the lander all the way to the wye for a spin without occupying and tying up the mains.