Steam & Excursion > ASR Reading 2100 Workday Report 04/22/2016


Date: 05/03/16 18:05
ASR Reading 2100 Workday Report 04/22/2016
Author: Erie2938K5a

Reading T-1 No.2100
Roundhouse Work Session Report for 04.22.2016
 
Volunteers
The following volunteers attended Saturday’s work session:
  • Steven Harvey
  • Eric Kapusta
  • Rick Owings
  • Brian Tusin
  • Paul Volosyn
  • Gordon Hartschuh
  • Kevin Anderson
  • Greg Brown
  • Tiffany Saultz
 
Work Report
This week saw the gridding for the ultrasound test being applied to the outside of the boiler.  The firebox area was completed and the boiler barrel was started by Paul, Gordon, and Greg.  Rick and Kevin spent the day starting to organize the spare parts, tools, etc. that are stored in the aux tender.  Brian ground dime size spots on the throat sheet inside the firebox for the ultrasounds readings.  At the moment almost half of the firebox has had the ultrasound testing performed on it.  The crown sheet, syphons, door sheet, and combustion chamber remain.  Contractor Jason Sobczynski and volunteer Brian machined the seats on five of the wash out plug seats using the portable Mill Hog.  The Mill Hog did a fabulous job, and saved tons of hours of labor.  Each seat that the Mill Hog cleaned up in 20 seconds would have taken 6 or more hours of time to do by hand.  We also featured our first live video on Facebook of a wash out plug seat being machined with the Mill Hog.  The reception to this was great, and we plan to do this again in the future.

Upcoming Events
  • The next work session is Saturday, May 14 2016 and starts at 9 am.
  • Don’t forget to come ready to sign and complete a volunteer waiver and if you are not a member already, come prepared to fill out a membership form and be able to pay your membership dues at that time.

Respectfully submitted,
 
Brian Tusin
Corresponding Secretary
 



Edited 1 time(s). Last edit at 05/03/16 18:20 by Erie2938K5a.








Date: 05/05/16 10:52
Re: ASR Reading 2100 Workday Report 04/22/2016
Author: Spikes

What State and City is the work site? Thanks. Best of luck! What is ASR?



Date: 05/05/16 10:59
Re: ASR Reading 2100 Workday Report 04/22/2016
Author: HotWater

Spikes Wrote:
-------------------------------------------------------
> What State and City is the work site? Thanks. Best
> of luck! What is ASR?

Google is your friend!



Date: 05/05/16 18:53
Re: ASR Reading 2100 Workday Report 04/22/2016
Author: TrackGuy

Spikes, ASR is short for "American Steam Railroad Preservation, Inc.".  To learn more about the project, go to www.fireup2100.org.  The restoration is taking place in Cleveland, OH.

Thanks,

TrackGuy