Eastern Railroad Discussion > Q: How will NS' ex-NKP Conneaut Creek Trestle be replaced?Date: 03/20/23 05:07 Q: How will NS' ex-NKP Conneaut Creek Trestle be replaced? Author: JPB NS has contracted with Mascaro Construction to replace the 1940-built ex-NKP Conneaut Creek trestle. Based on the link to the attached photo from Akron RR club, the replacement bridge piers are directly under the old bridge girders so the trestle is being built exactly where the original trestle is. Conneaut Creek Trestle replacement picture
Steel erecting should be starting in April per the Mascaro timeline. The timeline says "During Norfolk Southern Railway outages – anticipated as 24-hour continuous work, 2 shifts. Weekly Outages once per week maximum, forecasted to start Sunday or Monday, subject to NS traffic schedule" I wonder how Mascaro will execute the girder replacement with the old bridge still standing and in use? Here's a link to the approximate construction schedule timeline: Conneaut Creek Trestle replacement timeline Edited 1 time(s). Last edit at 03/20/23 05:08 by JPB. Date: 03/20/23 07:59 Re: Q: How will NS' ex-NKP Conneaut Creek Trestle be replaced? Author: CPR_4000 Looks like they've scheduled a 24-hour work window once a week for 13 weeks to install the steel. Guessing there are 13 spans? Apparently they'll replace one span a week for 13 weeks and then demolish the old trestle bents.
Date: 03/20/23 08:04 Re: Q: How will NS' ex-NKP Conneaut Creek Trestle be replaced? Author: leon If it is done like so many other railroad bridge replacements have been done, the new bridge will be wider
and the old bridge floor removed in one operation, the floor for the new bridge installed with expansion joints and attached to the to the new bridge foundation and girders. Date: 03/20/23 11:12 Re: Q: How will NS' ex-NKP Conneaut Creek Trestle be replaced? Author: CPR_4000 I'd think the new bridge will be a ballasted deck design, also.
Date: 03/21/23 08:32 Re: Q: How will NS' ex-NKP Conneaut Creek Trestle be replaced? Author: timz This is the one?
https://goo.gl/maps/BaEvNe5FCZSwKfDn8 It's going to get new piers? But the new track will be on the same alignment as now? |