The UP sent everyone by 4 or 5 PM yesterday. The box culvert has been installed under the mainline, slurry poured either side for back fill, steel plates attached to the open ends and base dumped on top.

Early today, they started dumping ballast, will pull the two panels [#1 & #2 tracks] back in place, dump more ballast with the loaders, tamp and make several raises and be ready to run trains. They will weld up the joints either today or in the near future.

I believe both #11 and 775 will run through tonight. The work train is parked on the #1 track with the power sitting above Castillo Street. My guess is a crew will be call later today to take the empty bulk head flats south to Oxnard/Gemco and or LA and east to Colton.

The project went very well and all hands seem very happy.



Date: 01/27/09 08:59
Re: Santa Barbara Update
Author: metrolinkvalleysub

Thank you for the update. Was Union Pacific replacing the bridge at the Santa Barbara Amtrak station?



Date: 01/27/09 12:21
Re: Santa Barbara Update
Author: P5r24

Yes,
Just S.P. west of the station.

Went thru there last Saturday 24th.
work train has 2 Aces for power.
Couldn't get the numbers while driving south on the 101 frwy
sorry,
Didn't have a camera.

P5r24



Date: 01/28/09 20:25
Re: Santa Barbara Update
Author: Josiah

UP was adding a second channel for Mission Creek under the tracks at the old Chapala Street grade crossing which was closed a number of years ago. County Flood Control is footing the bill. The original wooden bridge over the current Mission Creek channel 100 yards to the north was replaced June 2008.